Burnet Bay Storage (ERCOT-26INR0548) — Project Summary

Queue ID
ERCOT-26INR0548
Capacity
207.83 MW
Technology
Battery
Status
active
Location
Harris, TX
Region
ERCOT
Developer
TOCE TX BESS 4, LLC
IA Status
Facility Study

Burnet Bay Storage

ERCOT-26INR0548BetaActiveBatteryERCOTLBNL + Live

207.83 MW storage in Harris, TX · In queue since September 2024 · Proposed COD June 2027

207.83 MW

Capacity

1

Components

Battery

1y 8m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection

Total Duration

2y 9m

Facilities Study50%
Queue EntrySep 10, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-01

About

The Burnet Bay Storage project is a proposed 207.83 MW battery energy storage system located in Harris County, Texas. The project, developed by TOCE TX BESS 4, LLC, is interconnected within the Electric Reliability Council of Texas (ERCOT) region and identified in the ERCOT interconnection queue as entry 26INR0548. The project entered the queue on September 10, 2024, with a proposed commercial operation date of June 1, 2027.

The Burnet Bay Storage project's interconnection status is currently in the Facility Study phase. The point of interconnection (POI) is designated as tap 138kV 40390 Crosby - 40790 Haney. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Harris

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

TOCE TX BESS 4, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap 138kV 40390 Crosby - 40790 Haney

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_HOUSTON
Hub Confidence
MEDIUM
Nearest Node (Estimated)
CS_RN
POI Substation
Crosby Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Burnet Bay Storage