Texas Cotton Solar
201.6 MW generation in Brazos, TX · In queue since October 2024 · Proposed COD December 2026
201.6 MW
Capacity
1
Components
Solar
1y 7m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
2y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
The Texas Cotton Solar project is a proposed 201.6 MW solar generation facility in Brazos County, Texas. Developed by RWE Solar Development, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0568, with a queue entry date of October 1, 2024. The proposed commercial operation date is December 31, 2026.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 345kV 975 Jack_Creek - 967 Gibbons Creek. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Brazos
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
RWE Solar Development, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 975 Jack_Creek - 967 Gibbons Creek
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Texas Cotton Solar