Goat Mountain BESS
201.1 MW hybrid in Sterling, TX · In queue since January 2025 · Proposed COD June 2027
201.1 MW
Capacity
0
Components
1y 4m
In Queue
—
IA Status
COD target: 2027
Total Duration
2y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
The proposed Goat Mountain BESS project is a 201.1 MW hybrid battery energy storage system located in Sterling County, Texas. Developed by Goat Wind LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0589, with a queue entry date of January 28, 2025. The proposed commercial operation date is June 1, 2027, and the point of interconnection is the 76030-Gasconades Creek 345 kV substation.
The Goat Mountain BESS project is classified as a hybrid project consisting of battery energy storage. The project has appeared in recent news coverage regarding energy storage development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Sterling
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Goat Wind LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
76030-Gasconades Creek 345 kV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- GOA_GOATWIND
- POI Substation
- Gasconades Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.