Coda BESS
202 MW hybrid in San Patricio, TX · In queue since January 2025 · Proposed COD July 2028
202 MW
Capacity
0
Components
1y 4m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-31
The Coda BESS project is a proposed 202 MW hybrid battery energy storage system located in San Patricio County, Texas. Developed by Coda BESS, LLC, the project consists of battery energy storage paired with an unspecified "other" technology. It is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0599, with a queue entry date of January 28, 2025, and a proposed commercial operation date of July 31, 2028.
The point of interconnection for the project is the Mayo 138kV substation (#80258). The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
San Patricio
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Coda BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
(#80258) Mayo 138kV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.