Crocus Solar
102 MW generation in Stephens, TX · In queue since January 2025 · Proposed COD July 2028
102 MW
Capacity
0
Components
1y 4m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-01
The Crocus Solar project is a proposed 102 MW solar generation facility in Stephens County, Texas. The project, under development by Crocus Solar, LLC, consists of photovoltaic solar technology. It is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0600, with a queue entry date of January 28, 2025. The proposed commercial operation date is July 1, 2028.
The point of interconnection for the Crocus Solar project is the Tap 138 kV Gunsolas Creek Sub (1660) – Breckenridge Tap (1613). The project is listed as active in the ERCOT queue.
Generated from interconnection queue and public data sources
State
TX
County
Stephens
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Crocus Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV Gunsolas Creek Sub (1660) – Breckenridge Tap (1613)
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.