Damia Storage
153 MW hybrid in Eastland, TX · In queue since April 2025 · Proposed COD July 2028
153 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-01
The Damia Storage project is a proposed 153 MW hybrid battery energy storage project located in Eastland County, Texas. Developed by Damia Solar, LLC, the project consists of battery energy storage and other unspecified technologies. It is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0602, with a queue entry date of April 1, 2025, and a proposed commercial operation date of July 1, 2028.
The point of interconnection is Tap 138kV 6317 Cisco - 3545 MTNBRANCH_8.
Generated from interconnection queue and public data sources
State
TX
County
Eastland
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Damia Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 6317 Cisco - 3545 MTNBRANCH_8
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Damia Storage