Bell County Morgan Storage
256.4 MW storage in Bell, TX · In queue since November 2024 · Proposed COD April 2028
256.4 MW
Capacity
1
Components
Battery
1y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-01
The Bell County Morgan Storage project is a proposed 256.4 MW battery storage project located in Bell County, Texas. Developed by DM-BCTRM, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0615, with a queue entry date of November 19, 2024. The project's proposed commercial operation date is April 1, 2028, and its interconnection agreement status is currently in the Facility Study phase.
The project will interconnect at the To Tap 138 kV Trimmier Substation (Bus# 136). The development has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Bell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
DM-BCTRM, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
To Tap 138 kV Trimmier Substation (Bus# 136)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Oxy Tap Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.