Dempsey Solar SLF
245.34 MW generation in Leon, TX · In queue since February 2025 · Proposed COD September 2028
245.34 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-08
The Dempsey Solar SLF project is a proposed 245.34 MW solar generation project located in Leon County, Texas. Developed by Dempsey Solar LLC, the project is interconnected within the Electric Reliability Council of Texas (ERCOT) region. The proposed point of interconnection (POI) is at the Tap 138 KV Ridge (#37)-Robertson (#32) line; BEPC.
The project, identified by queue ID ERCOT-26INR0632, entered the ERCOT interconnection queue on February 25, 2025. The proposed commercial operation date (COD) is September 8, 2028. As of the current data, the project has an active status in the interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Leon
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Dempsey Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 KV Ridge (#37)-Robertson (#32) line; BEPC
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Dempsey Solar SLF