Lyra Storage
500 MW hybrid in Borden, TX · In queue since May 2025 · Proposed COD November 2026
500 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
Signed Aug 2025
Queue → IA
3 months
IA → COD
1y 3m
Total Duration
3 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-11-12
The Lyra Storage project is a proposed 500 MW hybrid battery energy storage system located in Borden County, Texas. Developed by JUNO BESS I, the project is interconnected within the ERCOT region and entered the ERCOT interconnection queue (ERCOT-26INR0636) on May 27, 2025. An Interconnection Agreement (IA) was executed on August 13, 2025. The proposed commercial operation date is November 12, 2026, with a point of interconnection at the 345kV MULESHOE substation.
The Lyra Storage project is currently listed as active in the ERCOT interconnection queue. The project utilizes battery energy storage technology, with "Other" specified as an additional technology detail.
Generated from interconnection queue and public data sources
State
TX
County
Borden
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
JUNO BESS I
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345kV MULESHOE (#59922)
Data Source
Live · ERCOT