Greyhound Solar - Phase E
150.71 MW generation in Ector, TX · In queue since April 2025 · Proposed COD November 2025
150.71 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
Signed Jan 2022
IA → COD
3y 10m
Total Duration
1y 1m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-11-20
Greyhound Solar - Phase E is a proposed solar generation project located in Ector County, Texas, with a total capacity of 150.71 MW. The project, developed by ROCKHOUND SOLAR 2 LLC DBA GREYHOUND SOLAR, consists of photovoltaic solar technology.
The project is listed in the ERCOT interconnection queue as entry ERCOT-26INR0669, with a queue entry date of April 17, 2025. The proposed commercial operation date is November 20, 2025, and the interconnection agreement date is January 15, 2022. The point of interconnection is at Tap 345kV 11010 Wolf - 1018 Moss.
Generated from interconnection queue and public data sources
State
TX
County
Ector
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
ROCKHOUND SOLAR 2 LLC DBA GREYHOUND SOLAR
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 11010 Wolf - 1018 Moss
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- WHCCS2_CC2
- POI Substation
- Wolf Hollow Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Greyhound Solar - Phase E