Zeus Mitchell BESS II
1,042.94 MW hybrid in Mitchell, TX · In queue since June 2025 · Proposed COD May 2027
1,042.94 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
COD target: 2027
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-01
The Zeus Mitchell BESS II project is a proposed 1042.94 MW hybrid battery energy storage project located in Mitchell County, Texas. Developed by Zeus Mitchell BESS II, LLC, the project consists of battery storage and other unspecified technologies. It is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0686, with a queue entry date of June 19, 2025, and a proposed commercial operation date of May 1, 2027.
The point of interconnection (POI) for the project is Tap 345 kV 10049 Ranger Camp - 10057 Prong Moss CKT #01 and #02.
Generated from interconnection queue and public data sources
State
TX
County
Mitchell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Zeus Mitchell BESS II, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 10049 Ranger Camp - 10057 Prong Moss CKT #01 and #02
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Range Camp Sub
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.