Puerto Del Sol 2
213.8 MW generation in Cameron, TX · In queue since May 2022 · Proposed COD December 2027
213.8 MW
Capacity
1
Components
Solar
4 years
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
The proposed Puerto Del Sol 2 project is a 213.8 MW solar generation project located in Cameron County, Texas. The developer is PUERTO DEL SOL, LLC. This project is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0002, with a queue entry date of May 16, 2022. The proposed commercial operation date is December 31, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection for Puerto Del Sol 2 is Tap 345kV 79500 Palmito - 79501 King Fisher Ckt 1. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Cameron
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
PUERTO DEL SOL, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 79500 Palmito - 79501 King Fisher Ckt 1
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Palmito Substation