Dundee North Wind
307.72 MW generation in Wilbarger, TX · In queue since January 2023 · Proposed COD December 2027
307.72 MW
Capacity
1
Components
Wind
3y 4m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
The Dundee North Wind project is a proposed 307.72 MW wind generation facility in Wilbarger County, Texas. Developed by Felix 2, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0004, with a queue entry date of January 3, 2023.
The proposed commercial operation date for Dundee North Wind is December 31, 2027. The project's interconnection status is currently in the Facility Study phase, and the point of interconnection is the 345 kV Riley Substation, operated by AEP. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Wilbarger
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Felix 2, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345 kV Riley Substation (#6101); AEP
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ELECTRAW_1_2
- POI Substation
- Riley Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.