Felix West Solar
200.95 MW generation in Wilbarger, TX · In queue since January 2023 · Proposed COD December 2028
200.95 MW
Capacity
1
Components
Solar
3y 4m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
5y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
The Felix West Solar project is a proposed 200.95 MW solar generation facility located in Wilbarger County, Texas. The project, developed by Felix 1, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0012, with a queue entry date of January 17, 2023. The proposed commercial operation date is December 31, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 6101 Riley 345 kV substation. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Wilbarger
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Felix 1, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6101 Riley 345 kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ELECTRAW_1_2
- POI Substation
- Riley Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Felix West Solar