Cumbia Energy Center (ERCOT-27INR0015) — Project Summary

Queue ID
ERCOT-27INR0015
Capacity
200 MW
Technology
Battery
Status
active
Location
Nueces, TX
Region
ERCOT
Developer
Cumbia Energy Center LLC
IA Status
Facility Study

Cumbia Energy Center

ERCOT-27INR0015BetaActiveBatteryERCOTLBNL

200 MW storage in Nueces, TX · In queue since March 2023 · Proposed COD September 2027

200 MW

Capacity

1

Components

Battery

3y 2m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection

Total Duration

4y 6m

Facilities Study50%
Queue EntryMar 27, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-09-07

About

The Cumbia Energy Center is a proposed 200 MW battery storage project located in Nueces County, Texas. Developed by Cumbia Energy Center LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-27INR0015, with an interconnection queue entry date of March 27, 2023. The proposed commercial operation date is September 7, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.

This development is linked to the existing Cumbia Energy Center operating plant (EIA ID 67768). The point of interconnection is the 8485 Westside Bulk 138kV substation, owned by AEP Texas Central Co. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Nueces

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Cumbia Energy Center LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

8485 Westside Bulk 138kV substation, owned by AEP Texas Central Co., bus number #

Data Source

LBNL

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
HIGH
Nearest Node (Estimated)
Westside_V_B
POI Substation
Westside Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Cumbia Energy Center