Live Oak Bayou Solar SLF
156.06 MW generation in Matagorda, TX · In queue since May 2023 · Proposed COD December 2027
156.06 MW
Capacity
1
Components
Solar
3 years
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
The Live Oak Bayou Solar SLF project is a proposed 156.06 MW solar generation facility in Matagorda County, Texas. Developed by FRESH AIR ENERGY II, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0021, with a queue entry date of May 15, 2023. The proposed commercial operation date is December 1, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection for the Live Oak Bayou Solar SLF project is Tap 345kV Refuge (42400) - Hawkinsville (42440) ckt 27.
Generated from interconnection queue and public data sources
State
TX
County
Matagorda
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
FRESH AIR ENERGY II, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV Refuge (42400) - Hawkinsville (42440) ckt 27
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Live Oak Bayou Solar SLF