Sunscape Renewable Energy Solar SLF (ERCOT-27INR0047) — Project Summary

Queue ID
ERCOT-27INR0047
Capacity
522.75 MW
Technology
Solar
Status
active
Location
Nueces, TX
Region
ERCOT
Developer
Sunscape Renewable Energy LLC
IA Status
IA Executed

Sunscape Renewable Energy Solar SLF

ERCOT-27INR0047BetaActiveSolarERCOTLBNL + Live

522.75 MW generation in Nueces, TX · In queue since June 2023 · Proposed COD January 2029

522.75 MW

Capacity

1

Components

Solar

2y 11m

In Queue

IA Executed

IA Status

Signed Jul 2024

Interconnection

Queue → IA

1y 1m

IA → COD

4y 6m

Total Duration

1y 1m

Construction75%
Queue EntryJun 28, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJul 18, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2029-01-26

About

Sunscape Renewable Energy Solar SLF is a proposed 522.75 MW solar generation project located in Nueces County, Texas. The project, developed by Sunscape Renewable Energy LLC, is interconnected within the ERCOT region under queue ID ERCOT-27INR0047. It entered the interconnection queue on June 28, 2023, with a proposed commercial operation date of January 26, 2029.

The project's Interconnection Agreement (IA) has been executed as of July 18, 2024. The point of interconnection is the Bus# 8455 Lon C Hill to Bus# 80078 Reforzar 345 kV Line. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Nueces

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Sunscape Renewable Energy LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Bus# 8455 Lon C Hill to Bus# 80078 Reforzar 345 kV Line

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
POI Substation
C

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.