Hecate Energy Orem Wind
1,542 MW generation in Brazoria, TX · In queue since June 2023 · Proposed COD June 2030
1,542 MW
Capacity
1
Components
Wind
2y 11m
In Queue
Facility Study
IA Status
COD target: 2030
Total Duration
7 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-06-01
The Hecate Energy Orem Wind project is a proposed wind generation project with a total capacity of 1542 MW. It is located in Brazoria County, Texas, and is being developed by Hecate Energy LLC. The project is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0061, with a queue entry date of June 28, 2023.
The proposed commercial operation date for the Hecate Energy Orem Wind project is June 1, 2030. Its interconnection agreement status is currently in the Facility Study phase. The point of interconnection is the 42530 Jones Creek 345kV location. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Brazoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Hecate Energy LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
42530 Jones Creek 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- DOW_61_2_63
- POI Substation
- Jones Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.