Laurel Storage Energy Center
200.8 MW storage in Pecos, TX · In queue since September 2023 · Proposed COD January 2027
200.8 MW
Capacity
1
Components
Battery
2y 8m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-01-31
The Laurel Storage Energy Center is a proposed 200.8 MW battery storage project located in Pecos County, Texas. The project, developed by Laurel Energy Center, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0080, with a queue entry date of September 7, 2023. The proposed commercial operation date is January 31, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.
The project consists of 200.8 MW of battery storage capacity. The point of interconnection is Tap 345kV 60404 Solstice - 76002 Bakersfield Ckt 2. The Laurel Storage Energy Center has been the subject of recent news coverage, with three articles categorized as industry and regulatory news.
Generated from interconnection queue and public data sources
State
TX
County
Pecos
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Laurel Energy Center, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 60404 Solstice - 76002 Bakersfield Ckt 2
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- HOVEY_GEN
- POI Substation
- Solstice Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Laurel Storage Energy Center