Aegle Power
1,536.4 MW generation in Cameron, TX · In queue since July 2024 · Proposed COD July 2027
1,536.4 MW
Capacity
1
Components
Gas
1y 10m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-30
Aegle Power LLC is proposing a 1536.4 MW gas-fired generation project called Aegle Power in Cameron County, Texas. The project is located within the ERCOT region and is interconnected at the (#79501) Kingfisher 345 kV point of interconnection. The project entered the ERCOT interconnection queue as ERCOT-27INR0084 on July 22, 2024, with a proposed commercial operation date of July 30, 2027. The project's interconnection status is currently in the Facility Study phase.
The Aegle Power project has been the subject of recent news coverage, with five articles focusing on regulatory matters and deals.
Generated from interconnection queue and public data sources
State
TX
County
Cameron
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Aegle Power LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
(#79501) Kingfisher 345 kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26