Eagle Claw Energy Center
200.84 MW storage in Grimes, TX · In queue since October 2023 · Proposed COD March 2028
200.84 MW
Capacity
1
Components
Battery
2y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-31
Eagle Claw Energy Center is a proposed 200.84 MW battery storage project located in Grimes County, Texas. The project, developed by Cypress Energy Center, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0085, with a queue entry date of October 13, 2023. The proposed commercial operation date is March 31, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection for Eagle Claw Energy Center is the 345 kV line between the Singleton (Bus #44645) and Zenith (Bus #44900) substations. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Grimes
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Cypress Energy Center, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
30.615932, -95.962023 - Singleton (Bus #44645) - Zenith (Bus #44900) Circuit #98 345 kV Line
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.