Two Barbaras BESS
217.16 MW storage in Montgomery, TX · In queue since March 2024 · Proposed COD January 2029
217.16 MW
Capacity
1
Components
Battery
2y 2m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-01-04
The Two Barbaras BESS project is a proposed 217.16 MW battery storage project located in Montgomery County, Texas. The developer is listed as Two Barbaras BESS. It is currently in the ERCOT interconnection queue as entry ERCOT-27INR0109, with a queue entry date of March 22, 2024, and a proposed commercial operation date of January 4, 2029. The project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection is the Tap 138 kV Pinehurst (#46240) _x0013_ Mill Creek (#44850) Line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Montgomery
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Two Barbaras BESS
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV Pinehurst (#46240) _x0013_ Mill Creek (#44850) Line
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Two Barbaras BESS