Paddlewheel Solar SLF
150 MW generation in Matagorda, TX · In queue since June 2024 · Proposed COD September 2027
150 MW
Capacity
1
Components
Solar
1y 11m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-30
Paddlewheel Solar SLF is a proposed 150 MW solar generation project located in Matagorda County, Texas. Developed by Paddlewheel Solar, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0122, with a queue entry date of June 3, 2024. The proposed commercial operation date is September 30, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 138 kV Pavlov Station (#8608) managed by AEP. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Matagorda
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Paddlewheel Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138 kV Pavlov Station (#8608); AEP
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Paddlewheel Solar SLF