RedSun Solar
82.55 MW generation in Burnet, TX · In queue since December 2023 · Proposed COD August 2028
82.55 MW
Capacity
1
Components
Solar
2y 5m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-08-28
The RedSun Solar project is a proposed 82.55 MW solar generation facility located in Burnet County, Texas. Developed by Gransolar Texas Twenty Two, the project consists of 82.55 MW of solar photovoltaic generation. It is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0124, with a queue entry date of December 4, 2023, and a proposed commercial operation date of August 28, 2028. The project's interconnection status is currently in the Facility Study phase.
The point of interconnection for the RedSun Solar project is Tap 138kV 7100 Burnet - 7529 Bertram. The project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Burnet
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Gransolar Texas Twenty Two
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 7100 Burnet - 7529 Bertram
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Burnet Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about RedSun Solar