Gatsby Energy Storage
103.36 MW storage in Pecos, TX · In queue since February 2024 · Proposed COD March 2027
103.36 MW
Capacity
1
Components
Battery
2y 3m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-03-31
The Gatsby Energy Storage project is a proposed 103.36 MW battery storage project located in Pecos County, Texas. Developed by Gatsby Energy Storage LLC, the project is interconnected within the ERCOT region and entered the ERCOT interconnection queue as queue ID ERCOT-27INR0139 on February 7, 2024. The proposed commercial operation date is March 31, 2027, and the project's interconnection status is currently in the Facility Study phase.
The proposed project is linked to the existing Gatsby Energy Storage Project operating plant (EIA ID 68428). Recent news coverage has discussed the development.
Generated from interconnection queue and public data sources
State
TX
County
Pecos
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Gatsby Energy Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Fort Lancaster 138 kV Substation (PSSE Bus #76579)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- HIGH
- POI Substation
- Fort Lancaster
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.