Angel City Solar
221.02 MW generation in Goliad, TX · In queue since February 2024 · Proposed COD September 2029
221.02 MW
Capacity
1
Components
Solar
2y 3m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-30
The proposed Angel City Solar project is a 221.02 MW solar generation facility in Goliad County, Texas. Developed by Angel City Energy Center, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0144, with a queue entry date of February 7, 2024. The proposed commercial operation date is September 30, 2029, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection (POI) is at Coleto Creek (# 8164) AEP and Pawnee (#5725) STEC, located 25.9 miles from Coleto Creek and 28.2 miles from Pawnee Substation. The POI coordinates are 28.755, -97.583. The Angel City Solar project has been mentioned in recent industry news.
Generated from interconnection queue and public data sources
State
TX
County
Goliad
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Angel City Energy Center, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Coleto Creek (# 8164) AEP _x0013_ Pawnee (#5725) STEC, 25.9 miles from Coleto Creek, 28.2 miles from Pawnee Sub. POI co-ordinates: 28.755, -97.583
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo ask pi reports yet for this entity.
ask pi about Angel City Solar