Larrea Solar
231.6 MW generation in Pecos, TX · In queue since January 2024 · Proposed COD September 2027
231.6 MW
Capacity
1
Components
Solar
2y 4m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-18
The Larrea Solar project is a proposed 231.6 MW solar generation facility in Pecos County, Texas. The project, developed by Greasewood IV LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0146, with a queue entry date of January 3, 2024. The proposed commercial operation date is September 18, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection is the Tap 345kV 76002 Bakerfield - 60404 Solstice CKT#1. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Pecos
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Greasewood IV LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 76002 Bakerfield - 60404 Solstice CKT#1
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.