Paloma Energy Center
193.8 MW generation in Colorado, TX · In queue since February 2024 · Proposed COD June 2027
193.8 MW
Capacity
1
Components
Solar
2y 3m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
The Paloma Energy Center is a proposed solar generation project with a total capacity of 193.8 MW, located in Colorado County, Texas. The project, being developed by Harrison Street Development, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0147, with a queue entry date of February 7, 2024. The proposed commercial operation date is June 1, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap138 kV 57640 Rock Island - 57639 Sheridan. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Colorado
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Harrison Street Development, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap138 kV 57640 Rock Island - 57639 Sheridan
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- SKY1
- POI Substation
- Rock Island Substation