Paloma Energy Center BESS
53.6 MW storage in Colorado, TX · In queue since February 2024 · Proposed COD June 2027
53.6 MW
Capacity
1
Components
Battery
2y 3m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
The Paloma Energy Center BESS is a proposed 53.6 MW battery storage project located in Colorado County, Texas. Developed by Harrison Street Development, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0148, with a queue entry date of February 7, 2024. The proposed commercial operation date is June 1, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 138 kV Tap 57640 Rock Island and 57639 Sheridan. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Colorado
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Harrison Street Development, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138 kV Tap 57640 Rock Island and 57639 Sheridan
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Paloma Energy Center BESS