Diablo Campo Storage
313.54 MW storage in Goliad, TX · In queue since February 2024 · Proposed COD September 2029
313.54 MW
Capacity
1
Components
Battery
2y 3m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-30
The Diablo Campo Storage project is a proposed 313.54 MW battery energy storage system located in Goliad County, Texas. The project, developed by Diablo Campo Energy Center, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0149, with a queue entry date of February 7, 2024. The proposed commercial operation date is September 30, 2029.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is listed as The Coleto Greek (#8164) to Pawnee Switching Station (#5725) with LCRA. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Goliad
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Diablo Campo Energy Center, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
The Coleto Greek (#8164) to Pawnee Switching Station (#5725) ; LCRA
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Pawnee
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.