Cielo Vista Solar
503.34 MW generation in Duval, TX · In queue since April 2025 · Proposed COD June 2028
503.34 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
Cielo Vista Solar, LLC is proposing a 503.34 MW solar photovoltaic generation project in Duval County, Texas. The project, named Cielo Vista Solar, is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0150, with a queue entry date of April 21, 2025. The proposed commercial operation date is June 30, 2028.
The point of interconnection for the proposed project is Tap 345kV Bus #5901 Miguel5 - Bus #80079 Cruce7A Ckt 1. The project is listed as active in the ERCOT queue.
Generated from interconnection queue and public data sources
State
TX
County
Duval
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Cielo Vista Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV Bus #5901 Miguel5 - Bus #80079 Cruce7A Ckt 1
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the powerplantsinfo.org database.
Compare Texas vs California solar
Summary analysis with parallel narrative sections and visualizations.
Top 10 solar states
Data tables and metrics from the powerplantsinfo.org database.