Trenno BESS (ERCOT-27INR0173) — Project Summary

Queue ID
ERCOT-27INR0173
Capacity
202.56 MW
Technology
Battery
Status
active
Location
Johnson, TX
Region
ERCOT
Developer
JSB1, LLC
IA Status
Facility Study

Trenno BESS

ERCOT-27INR0173BetaActiveBatteryERCOTLBNL + Live

202.56 MW storage in Johnson, TX · In queue since February 2024 · Proposed COD September 2027

202.56 MW

Capacity

1

Components

Battery

2y 3m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection

Total Duration

3y 7m

Facilities Study50%
Queue EntryFeb 7, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-09-13

About

The Trenno BESS project is a proposed 202.56 MW battery storage project located in Johnson County, Texas. Developed by JSB1, LLC, the project consists entirely of battery storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0173, with a queue entry date of February 7, 2024.

The proposed commercial operation date for the Trenno BESS project is September 13, 2027. Its interconnection status is currently in the Facility Study phase, and the point of interconnection is Tap 138kV 2281 Godley - 2888 Carmichael.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Johnson

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

JSB1, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 138kV 2281 Godley - 2888 Carmichael

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Trenno BESS