Cedar Draw BESS
225.7 MW storage in Scurry, TX · In queue since March 2024 · Proposed COD December 2027
225.7 MW
Capacity
1
Components
Battery
2y 2m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
The Cedar Draw BESS project is a proposed 225.7 MW battery storage project located in Scurry County, Texas. Developed by Cedar Draw Solar LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0193, with a queue entry date of March 22, 2024. The proposed commercial operation date is December 31, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 60011 Nebula7A 345kV location. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Scurry
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Cedar Draw Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
60011 Nebula7A 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Cedar Draw BESS