CORRUSCANT BESS
337.35 MW storage in Dickens, TX · In queue since February 2024 · Proposed COD April 2027
337.35 MW
Capacity
1
Components
Battery
2y 3m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-18
The proposed CORRUSCANT BESS project is a 337.35 MW battery storage development in Dickens County, Texas. The project, being developed by AEU Battery Project III LLC, is located within the ERCOT region and consists entirely of battery storage.
The project is listed in the ERCOT interconnection queue as entry ERCOT-27INR0195, with a queue entry date of February 27, 2024. Its proposed commercial operation date is April 18, 2027, and its interconnection agreement status is currently in the Facility Study phase. The point of interconnection is Tap 345kV 59904 COTTONWOOD - 60500 EDITHCLA7A.
Generated from interconnection queue and public data sources
State
TX
County
Dickens
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
AEU Battery Project III LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 59904 COTTONWOOD - 60500 EDITHCLA7A
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Cottonwood Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.