Themisto Solar
301.2 MW generation in Nolan, TX · In queue since February 2024 · Proposed COD June 2028
301.2 MW
Capacity
1
Components
Solar
2y 3m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
Themisto Solar is a proposed 301.2 MW solar generation project located in Nolan County, Texas. The project, developed by Themisto Solar, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0218, with a queue entry date of February 26, 2024. The proposed commercial operation date is June 30, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 345kV Champion Creek #1414 _x0013_ Sweetwater East #11420. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Nolan
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Themisto Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV Champion Creek #1414 _x0013_ Sweetwater East #11420
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.