Benitoite Storage
125.65 MW storage in Van Zandt, TX · In queue since March 2024 · Proposed COD August 2027
125.65 MW
Capacity
1
Components
Battery
2y 2m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-08-25
The Benitoite Storage project is a proposed 125.65 MW battery energy storage system in Van Zandt County, Texas. Developed by BT Van Storage, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0223, with a queue entry date of March 22, 2024. The proposed commercial operation date is August 25, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 138kV 3183 VAN_8 - 3197 TYLERSW_8. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Van Zandt
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BT Van Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 3183 VAN_8 - 3197 TYLERSW_8
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Benitoite Storage