Sunlit Pines Solar SLF (ERCOT-27INR0226) — Project Summary

Queue ID
ERCOT-27INR0226
Capacity
206.71 MW
Technology
Solar
Status
active
Location
Nacogdoches, TX
Region
ERCOT
Developer
Sunlit Pines Energy Center LLC
IA Status
Facility Study

Sunlit Pines Solar SLF

ERCOT-27INR0226BetaActiveSolarERCOTLBNL + Live

206.71 MW generation in Nacogdoches, TX · In queue since March 2024 · Proposed COD September 2028

206.71 MW

Capacity

1

Components

Solar

2y 2m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection

Total Duration

4y 6m

Facilities Study50%
Queue EntryMar 29, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-09

About

The Sunlit Pines Solar SLF project is a proposed 206.71 MW solar generation project located in Nacogdoches County, Texas. The project, developed by Sunlit Pines Energy Center LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0226, with a queue entry date of March 29, 2024. The proposed commercial operation date is September 9, 2028, and the project is currently in the Facility Study phase of its Interconnection Agreement (IA) process.

The point of interconnection (POI) is Tap 138 kV 3342 Bayou Loco - 3341 Central Angelina County.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Nacogdoches

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Sunlit Pines Energy Center LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 138 kV 3342 Bayou Loco - 3341 Central Angelina County

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Sunlit Pines Solar SLF