Anawa La BESS (ERCOT-27INR0233) — Project Summary

Queue ID
ERCOT-27INR0233
Capacity
103.7 MW
Technology
Battery
Status
active
Location
Hidalgo, TX
Region
ERCOT
Developer
EIA Properties, Ltd.
IA Status
Facility Study

Anawa La BESS

ERCOT-27INR0233BetaActiveBatteryERCOTLBNL + Live

103.7 MW storage in Hidalgo, TX · In queue since March 2024 · Proposed COD August 2027

103.7 MW

Capacity

1

Components

Battery

2y 2m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection

Total Duration

3y 5m

Facilities Study50%
Queue EntryMar 22, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-08-31

About

The Anawa La BESS project is a proposed 103.7 MW battery storage project located in Hidalgo County, Texas. The developer is EIA Properties, Ltd. It is currently in the ERCOT interconnection queue as entry ERCOT-27INR0233, with a queue entry date of March 22, 2024. The proposed commercial operation date is August 31, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.

The project consists of 103.7 MW of battery storage capacity. The point of interconnection is Tap 138KV 8394 Liston- 8392 Bates. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Hidalgo

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

EIA Properties, Ltd.

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 138KV 8394 Liston- 8392 Bates

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
LV5_UNIT1
POI Substation
Liston Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Anawa La BESS