Pez Rojo BESS
217.23 MW storage in Harris, TX · In queue since July 2024 · Proposed COD February 2029
217.23 MW
Capacity
1
Components
Battery
1y 10m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-02-01
The Pez Rojo BESS project is a proposed 217.23 MW battery storage project located in Harris County, Texas. The developer is Pez Rojo BESS, LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0245, with a queue entry date of July 1, 2024.
The proposed commercial operation date for the Pez Rojo BESS project is February 1, 2029. Its interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 138 kV #40260 Chamon - #40912 King.
Generated from interconnection queue and public data sources
State
TX
County
Harris
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pez Rojo BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV #40260 Chamon - #40912 King
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.