122.3 MW storage in Jackson, TX · In queue since June 2024 · Proposed COD May 2027
122.3 MW
Capacity
1
Components
Battery
1y 11m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-31
Sayle Storage is a proposed 122.3 MW battery storage project located in Jackson County, Texas. The project, being developed by Sayle Storage LLC, is currently in the ERCOT interconnection queue as entry ERCOT-27INR0260, with a queue entry date of June 3, 2024. The proposed commercial operation date is May 31, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.
The Sayle Storage project consists of 122.3 MW of battery storage capacity. Recent news coverage indicates activity related to the project in both regulatory and industry contexts.
Generated from interconnection queue and public data sources
State
TX
County
Jackson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Sayle Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 69kV #5522 Edna - #5518 El Toro SW
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Sayle Storage