XE Flying Kite Bess
104.73 MW storage in Zavala, TX · In queue since July 2024 · Proposed COD December 2027
104.73 MW
Capacity
1
Components
Battery
1y 10m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-30
The XE Flying Kite Bess project is a proposed 104.73 MW battery storage project located in Zavala County, Texas. The developer is Flying Kite BESS, LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0274, with a queue entry date of July 30, 2024.
The proposed commercial operation date for the XE Flying Kite Bess project is December 30, 2027. Its interconnection status is currently in the Facility Study phase. The point of interconnection is at tap 69kV 8672 La Pryor - 8231 Uvalde.
Generated from interconnection queue and public data sources
State
TX
County
Zavala
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Flying Kite BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 69kV 8672 La Pryor - 8231 Uvalde
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.