Rain Lily Storage 1
105.6 MW hybrid in Hood, TX · In queue since February 2025 · Proposed COD October 2028
105.6 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-15
Rain Lily Storage 1 is a proposed 105.6 MW hybrid energy project consisting of battery storage, located in Hood County, Texas. The project, developed by Rain Lily Storage One, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0285, with a queue entry date of February 25, 2025. The proposed commercial operation date is October 15, 2028.
The project will interconnect at Tap 138kV #350 ABBYBEND - #363 HOOD.
Generated from interconnection queue and public data sources
State
TX
County
Hood
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Rain Lily Storage One, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV #350 ABBYBEND - #363 HOOD
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Rain Lily Storage 1