Nouveau BESS
256.1 MW storage in Brown, TX · In queue since August 2024 · Proposed COD December 2027
256.1 MW
Capacity
1
Components
Battery
1y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-15
The Nouveau BESS project is a proposed 256.1 MW battery storage project located in Brown County, Texas. Developed by RamZ BESS, LLC, the project consists of 256.1 MW of battery capacity.
The project is listed in the ERCOT interconnection queue as entry ERCOT-27INR0291, with a queue entry date of August 16, 2024, and a proposed commercial operation date of December 15, 2027. Its interconnection agreement status is currently in the Facility Study phase. The point of interconnection is the 1444 Brown Switch - 3348 Russell Gap 345 kV Line.
Generated from interconnection queue and public data sources
State
TX
County
Brown
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
RamZ BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1444 Brown Switch - 3348 Russell Gap 345 kV Line
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.