Donelson Storage SLF
— hybrid in Red River, TX · In queue since March 2025 · Proposed COD October 2028
—
Capacity
0
Components
1y 2m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-17
The Donelson Storage SLF project is a proposed hybrid battery storage project located in Red River County, Texas. The project, developed by Donelson Storage, has a total capacity that is not specified in the provided data. It is interconnected within the ERCOT region under queue ID ERCOT-27INR0293, with a queue entry date of March 24, 2025.
The proposed commercial operation date (COD) for the Donelson Storage SLF project is October 17, 2028. The point of interconnection (POI) is at a tap on the 69 kV Bagwell to Clarksville line operated by ONCOR. The interconnection agreement (IA) status is not specified in the provided data. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Red River
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Donelson Storage
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap the 69 kV Bagwell (#1785) - Clarksville (#11784) line, ONCOR
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.