Tolivar Power Plant (TEF- Due Diligence)
225.6 MW generation in Reeves, TX · In queue since July 2024 · Proposed COD May 2027
225.6 MW
Capacity
1
Components
Gas
1y 10m
In Queue
IA Executed
IA Status
Signed Nov 2024
Queue → IA
4 months
IA → COD
2y 6m
Total Duration
4 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2027-05-06
The Tolivar Power Plant (TEF- Due Diligence) is a proposed project located in Reeves County, Texas, within the ERCOT region. Developed by Pecos Power Plant, LLC, the project consists of 225.6 MW of gas-fired generation. It entered the ERCOT interconnection queue as project ERCOT-27INR0297 on July 1, 2024, with a proposed commercial operation date of May 6, 2027.
The project's Interconnection Agreement (IA) has been executed as of November 12, 2024. The point of interconnection (POI) is Tap 138 KV 38045 IH20-38043 COWPEN.
Generated from interconnection queue and public data sources
State
TX
County
Reeves
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pecos Power Plant, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 KV 38045 IH20-38043 COWPEN
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.