Symank Solar
66.55 MW generation in Bosque, TX · In queue since November 2024 · Proposed COD December 2027
66.55 MW
Capacity
1
Components
Solar
1y 6m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-15
The Symank Solar project is a proposed 66.55 MW solar generation facility in Bosque County, Texas. Developed by BT Symank Solar, LLC, the project entered the ERCOT interconnection queue as ERCOT-27INR0298 on November 19, 2024. Its proposed commercial operation date is December 15, 2027, and its interconnection agreement status is currently in the Facility Study phase. The point of interconnection is at Tap 69 kV 37470 TNOLSEN - 37520 TNSYCAMORE.
The proposed project is linked to the existing Symank Solar operating plant (EIA ID 68175). The project has also appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Bosque
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BT Symank Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 69 kV 37470 TNOLSEN - 37520 TNSYCAMORE
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Symank Solar