Fletcher BESS
309.92 MW storage in Harris, TX · In queue since July 2024 · Proposed COD July 2027
309.92 MW
Capacity
1
Components
Battery
1y 10m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-02
The Fletcher BESS project is a proposed 309.92 MW battery storage project located in Harris County, Texas. Developed by Archer Energy Center, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0304, with a queue entry date of July 22, 2024. The proposed commercial operation date is July 2, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.
The project consists solely of battery storage with a total capacity of 309.92 MW. The point of interconnection is Tap 138 kV 44630 Garth _x0013_ 48156 Highlands. The Fletcher BESS project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Harris
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Archer Energy Center, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV 44630 Garth _x0013_ 48156 Highlands
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.