Edgewood BESS 1 (ERCOT-27INR0317) — Project Summary

Queue ID
ERCOT-27INR0317
Capacity
100.3 MW
Technology
Battery
Status
active
Location
Van Zandt, TX
Region
ERCOT
Developer
Tempus Power management LLC
IA Status
Facility Study

Edgewood BESS 1

ERCOT-27INR0317BetaActiveBatteryERCOTLBNL + Live

100.3 MW storage in Van Zandt, TX · In queue since November 2024 · Proposed COD March 2028

100.3 MW

Capacity

1

Components

Battery

1y 6m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection

Total Duration

3y 4m

Facilities Study50%
Queue EntryNov 21, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-03-01

About

The Edgewood BESS 1 project is a proposed 100.3 MW battery storage project located in Van Zandt County, Texas. The developer is Tempus Power Management LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0317, with a queue entry date of November 21, 2024. The proposed commercial operation date is March 1, 2028, and the project is currently in the Facility Study phase of its Interconnection Agreement.

The project consists of 100.3 MW of battery storage capacity. The point of interconnection is the Tap Edgewood 138kV bus(3181) to CANTNSW_8 (3174). The Edgewood BESS 1 project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Van Zandt

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Tempus Power management LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap Edgewood 138kV bus(3181) to CANTNSW_8 (3174)

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Edgewood BESS 1