166 MW generation in Morris, TX · In queue since September 2024 · Proposed COD May 2028
166 MW
Capacity
1
Components
Gas
1y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-11
The LONE STAR INDUSTRIAL PARK GAS POWER PROJECT (TEF-Due Diligence), identified as ERCOT-27INR0324 in the ERCOT interconnection queue, is a proposed 166 MW gas-fired generation project in Morris County, Texas. Developed by LONE STAR INDUSTRIAL PARK, LLC, the project entered the queue on September 4, 2024, with a proposed commercial operation date of May 11, 2028. The project's interconnection status is currently in the Facility Study phase.
The proposed project consists of 166 MW of gas-fired capacity. It is slated to connect to the 1795 Monticello SES 138kV point of interconnection. Recent news coverage indicates activity related to deals involving the project.
Generated from interconnection queue and public data sources
State
TX
County
Morris
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
LONE STAR INDUSTRIAL PARK, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1795 Monticello SES 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Monticello substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.