Hamlet Solar
204 MW generation in Frio, TX · In queue since November 2024 · Proposed COD September 2029
204 MW
Capacity
1
Components
Solar
1y 6m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-04
Hamlet Solar is a proposed 204 MW solar generation project located in Frio County, Texas. The project, being developed by Hamlet Solar, LLC, is interconnected within the Electric Reliability Council of Texas (ERCOT) queue as entry ERCOT-27INR0362, with a queue entry date of November 19, 2024. The proposed commercial operation date is September 4, 2029, and the project's interconnection status is currently in the Facility Study phase.
The proposed project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Frio
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Hamlet Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV #5895 PEARSALL - #5827 MOORE
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26